Job costing for small contractors: a simple weekly method

Job costing means putting every cost on the job it was spent on - labor hours, materials, equipment rental, subcontractors and small expenses - and comparing it every week with what the client has paid and the contract value. For a small crew, four lists are enough: daily time per job, materials delivered per job, other costs per job, and payments received per job.

Last updated:

The four lists

  • Time: who worked on which job each day, with overtime.
  • Materials: what was delivered to which job, with the delivery ticket number and price.
  • Other costs: dumpster, permits, equipment rental, fuel, small tools - each with its job.
  • Money in: deposits, draws and final payments per job.

The weekly check (15 minutes)

Per jobQuestion
Received - spentIs this job paying for itself so far?
Labor vs estimateAre we over on hours?
Materials on siteIs stock sitting idle or going missing?
Contract - receivedWhat's left to bill, and when?

Common mistakes

  • Leaving labor to month-end payroll: by then the job is over budget.
  • Buying for one job and using it on another without moving the cost.
  • Forgetting shared costs: keep them separate, don't hide them in one job.

Frequently asked questions

Do I need accounting software for this?

Your accountant's software handles taxes and the books. Job costing is a daily habit on site; a simple app or sheet that ties time, material and payments to each job is enough.

How is this different from estimating?

Estimating is the price before the job; job costing is what actually happened, checked while there's still time to act.