1. One worker list
- Name, phone, trade (mistri, helper, carpenter...), crew or mukadam, and the agreed daily rate.
- Monthly staff (munshi, supervisor): salary per month; for part months use salary / 30 per day - and say so when hiring.
- When a rate changes, note the date: old days stay at the old rate.
2. Hajri every day, at the site
- Present = 1 day, half day = 0.5, absent = 0. Overtime in hours.
- Mark it at the site at the same time every day; a register filled from memory on Saturday is where "24 days vs 21 days" starts.
- One worker, one entry per day - if they moved sites, mark them where they worked.
3. Kharchi (advance) the same day
- Date, worker, amount, cash or UPI, and who gave it - supervisor petty cash included.
- Never "I'll remember": an advance not written is the most common settlement fight.
4. Settlement
On your fixed day (weekly or monthly):
| Item | Example |
|---|---|
| Days (24 full + 2 half) | 25 days |
| x daily rate | x 800 = 20,000 |
| + overtime (10 h x 800 / 8) | + 1,000 |
| - advances | - 5,000 |
| = to pay | 16,000 |
5. Show it, then pay
- Read out or send the days, overtime, advances and balance before paying.
- Keep the month's muster roll and the payments list - the next dispute is settled in a minute.
Frequently asked questions
How is overtime calculated?
Most contractors pay daily rate / hours in a day for each overtime hour; some pay 1.5x or 2x. Agree it before work starts - the wage calculator shows both.
What if a worker says I gave less advance?
Only a written entry - date, amount, who gave it - settles it. Write it the same day; if you use an app, the worker can be sent the list.
Is this about minimum wage or PF / ESI?
No - this is day-to-day bookkeeping. Minimum wages, PF, ESI and labour licences depend on your state and the job size; ask your accountant.